8th Street Water Main: Planned Work For Week Commencing 10/8

The NYC Department of Design & Construction have advised the following works will take place between 10/8 and 10/12 to replace the Eighth Street water main. 

Tuesday 10/9 - Friday 10/12 from 7:00am-3:30pm

- 12" Water Main Installation on West 8th Street between MacDougal Street and Sixth Avenue.

- 12" Water Main Installation on West 8th Street between MacDougal Street and Fifth Avenue.

- Saw Cutting for Test Pits / Trench Excavation on East 8th St. between Fifth Avenue and University Place.

No work is scheduled for Monday 10/9 due to the Columbus Day Holiday.

Water Supply Interruption

There are planned water supply interruption's daily between 7:00am and 2:00pm on West 8th between MacDougal Street and Sixth Avenue AND on West 8th Street between MacDougal Street and Fifth Avenue. 

Water shutdowns are expected throughout the week. A 24-hour confirmation notice will be provided daily to all affected properties.

For further information contact the DDC Community Relations Manager, Myriam Benjamin. Phone; 212-643-1654, email; meda003ccl@gmail.com. 