Construction Date To Replace 8th Street Water Main Confirmed

The NYC Department of Design & Construction (DDC) have confirmed that construction work for the 8th Street Water Main Replacement Project will commence on Monday, September 17th.  

Initial Works 

  • Tree pruning, removals, and saw cutting.
  • Digging small test pits to determine what infrastructure is below ground. 

Thereafter digging of the main larger trench will commence, beginning at the Sixth Avenue end of 8th Street, gradually moving towards Broadway. 

Hours of Construction 

  • Monday to Friday, 7:00am to 3:30pm. 
  • Saturday hours may vary.
  • Working hours are subject to weather conditions.

Water Supply Interruptions 

  • At this time there are no planned water shutdowns.
  • When water shutdowns are required, the project contractor, NYC Department of Design & Construction (DDC) will provide a 72 hour e-mail notification.

Project Partners 

  • This project has been commissioned by the NYC Department of Environmental Protection.
  • The DDC Community Relations Manager, Myriam Benjamin is yours, and our, first point of contact for questions relating to construction and site conditions. Phone; 212-643-1654, email; meda003ccl@gmail.com 
  • During the project the Village Alliance will advocate for businesses and residents alike, working with DEP and DDC to ensure disruption is kept to a minimum. 

Further Information

The Village Alliance is open Monday - Friday 9:30am - 6:00pm. Please feel free to visit or call us anytime to discuss concerns and questions you may have.

Construction Date To Replace 8th Street Water Main Confirmed

Comments

  1. 2 Fifth Ave. resident
    2 Fifth Ave. resident on 09/15/2018 11:48 p.m.

    Why are we hearing about this only now, for the first time, literally a few days before it starts???
    How will this affect traffic on 8th Street? Will it remain open? And will this be finished before the upcoming traffic nightmare due to the L train shutdown begins? I assume not -- so why was there no coordination between the DDC, the DOT, and the MTA as to the timing of this project?

  2. Buy Gmail Accounts
    Buy Gmail Accounts on 09/16/2018 11:49 a.m.

    I finally found the great post here. I will get back here. I just added your blog to my bookmark sites. thanks. Quality posts are crucial to invite the visitors to visit the web page, that's what this web page is providing.

  3. zoomtargets
    zoomtargets on 09/16/2018 11:50 a.m.

    You actually make it look so easy with your performance but I find this matter to be actually something which I think I would never comprehend. It seems too complicated and extremely broad for me. I'm looking forward to your next post, I’ll try to get the hang of it!

  4. Iphone XC review
    Iphone XC review on 09/16/2018 11:51 a.m.

    Really impressed! Everything is very open and very clear clarification of issues. It contains truly facts. Your website is very valuable. Thanks for sharing.

  5. Mcafee Activate Login
    Mcafee Activate Login on 09/17/2018 4:54 a.m.

    Impressive content by Admin and thanks for sharing with us By the way, if you are a McAfee antivirus user and you want to expand your subscription or renew your subscription then visit at Mcafee Activate

  6. top biz op
    top biz op on 09/23/2018 3:03 p.m.

    I read your website as often as possible and I just thought I'd say keep up the astonishing work!


Post your comment